In light of the other build threads (all of which look to have required substantially more labor than the room I setup), I figure maybe another Start to Finish thread would help keep the fire lit under those in the middle of their own build.
I'll start with the site work, stub-ups and foundation.
The only portions I subbed out were concrete and the actual structure. Concrete guy was jam up and the building guys steamrolled it. Five-ish month wait for structure, but once it was started it didn't take 10 hours until they completed the shell.
This project was done between January and September of 2020.