I am not posting many pics right now cause the table is currently torn apart for some a rebuild and It also past time for a paint and re-deco...
When we bought the house we got lucky that the back wall was 20 feet wide and the roof sloped to each side (instead of sloping toward the back)
back of the house also was the master bedroom.....I did some research and found a general contractor that could do the job...We found out that we could extend back 16 feet without violating any zoning laws.....(net 16 x 20 room addition)
I had to have an architect do official plans done for the permits and also for the association...the outside had to look exactly like the rest of the house for the association to approve it..(same roof tile, stucco, color) ...We got all the pre-approvals and off we went.
The contractor did not take all the money at once..I set up a separate account that I could draw from to pay him as he needed money for jobs.
All of the jobs (except the foundation) was done by crews that worked for companies but did side jobs in the afternoon after thier normal work day.
The foundation took the longest....they dug a pretty deep ditch around the outside of the new additon and loaded it up with all kinds of rebar...they poured it and the adjoining patio that now ties in with the origonal patio all at once..they added some studs around the edge for the walls...It was over a month before any other work was done.....
One afternoon a lumber drop was done into my back yard...The next afternoon 4 guys showed up and started throwing wood around and metal brackets and such...It seemed like only about an hour later they had the framing up and done for all three walls.
A couple days later the pre-built certified roof trusses were brought in from somewhere and installed......Then the electrician came back.....then a whole host of crews, plumber, stucco guys, insulation, roofer, drywall, glass door installer, AC, painter, electrician again...etc.etc.
It was done quicker than I thought is would be....Then the permit guy again came out and gave the final sign off...
$14k later (and another 1k for the GCII) I now have direct access from the master bedroom to a 16x20 pool room...The other access is from the back patio.
I had heard of horror stories of people doing something like this...work getting half completed or not completed at all...but I did not have any of those problems... In fact...about 6 months after the room addition was done the contractor called me to see if I had any problems.
The real luck in all this though was having a wife that will agree to let me spend 15K on a pool room.....:wink: