So that's the way you say his name. Or is it?
............................
Last edited:
So that's the way you say his name. Or is it?
Two man days. Guess I need to speed up my prosesses. Wonder how long it took him to get all those little pieces to where the are now and build the jigs to make all those little pieces! Damn I better get to work!
Larry
This may be a better question for the "Ask the Cue Maker" section, but it doesn't get a lot of traffic. We always bellyache when we don't get our cue on time, so how long does it really take?
If a cue maker could work 8 hours/day on a cue how long would it take before it's ready for delivery? This is from rough wood to finished product. I understand that cues and makers are all different. For example; how many inlays, if you use a pre-made blank, wrap vs wrapless, etc.
For this example lets say it's a 4 point cue, full splice that the maker builds, wrap, no inlays, and delrin buttcap with bumper. This assumes that the maker has shafts ready for final turning and doesn't have to go through that whole process. What do you think?
Edit: By the way, this is not directed at any cue maker and I don't have a cue being built right now. Just an honest question to satisfy my curiosity.
Woof biscuit if you send me your Scruggs you can
order yourself something new and put your question
to the test . Hope all is well. :thumbup:
"Most cue makers have a "stock pile" of splices and shafts to work with"
--------------------------------------------------------------------------------------------------------
Is that so?
If you know this much about the process - why did you need to ask the question??
In point of fact, actually building the cue is only part of what we have to do to produce cues.
IMHO - most cuemakers who do it for a living would consider 40 hours a week to be
'on vacation'
YMMV
Dale
It can take any where from 8-100 working hours depending on the design and complexity of the cue.
Some cue makers insist on insanely long resting periods between turnings for the woods.
I mean if a cue maker wanted to make you a plain jane or had splices etc already done, and they were working on just your cue, a reasonable time frame would be 2-8 weeks.
That's not how it works though, and most cue makers who are worth their salt have a back log so you should expect 3-9 months at a minimum...
Jaden
Calm down. No need to get sensitive. It was really an honest question. Maybe you don't have parts ready to go but some do. I done seen it!
I see what you mean if you have to build the splice. Thanks for the response. Most cue makers have a "stock pile" of splices and shafts to work with. The only problem is you may not be able to pick out the veneer colors and woods you want. So if you had it all ready to go and you'd done all of your seasoning on the front end, 12 hours is about right?
Calm down. No need to get sensitive. It was really an honest question. Maybe you don't have parts ready to go but some do. I done seen it!
If I work only 50 hours a week on cues and have 2 weeks a year vacation then there are 2500 hours used and I build 50 cues, it comes to 50 hours per cue on average. Cue making is like every other business, paper work, shipping, cleaning, emails, phones, etc are all part of the business of building cues. A simple answer isn't simple. I do have a large selection of parts ready to go when the cue is ordered, shafts, handles, ferrules, veneers, milled fronts, etc but I had to make all these parts in the years preceding the order, that time has to count too.
I would be concerned if I was told I would get a cue in less than 9 months.